Dry placement methods shall only be carried out when the excavation is dry (< 100mm of water at the bottom of the pile bore prior to concrete placement).

Direct placement with a shute is only permitted if the concrete won't segregate by hitting the reinforcement cage. I would suggest to use a discharge pipe for dry pours (e.g. lay flat tremie or steel tube)